Update to Guidance Notes 1.6 and 1.7

4 June 2025

As part of the ongoing review of the Capital Works Management Framework, Guidance Note 1.6 relating to procurement of Consultants and Guidance Note 1.7 relating to the Standard Conditions of Engagement and Sample Schedules have been reviewed and consolidated into a single guidance note and associated appendices. Continue reading

Change to minimum permitted tendered percentage addition to costs of labour

9 January 2025

OGP have published changes to the Forms of Tender and Schedule.

Schedule Part 2 D – Adjustments to the Contract Sum including Delay Costs (Sub-clause 10.6 and 10.7) – of the Form of Tender and Schedule provides the opportunity for the contractor to tender a percentage addition for labour costs as defined by the applicable sectoral employment order made under the Industrial Relations Acts 1946-2015. Continue reading